Chios Island National Airport “Omiros” · LGHI / JKH · updated 8 Oct 2026
One island.One runway.Four months, maybe more, with no flights.
The Chios runway is being lengthened from 1,511 m to 1,799 m. The works are needed. The island was promised a two-month full closure in January and February 2027. A scenario now under discussion would shut the airport from 15 November 2026 until spring 2027. This is the story of how that happened, and an invitation from one resident to look together at another way.
Where things stand
On 6 October 2026 local press reported a full closure from 15 November until spring. No NOTAM has been issued and the contractor declines to comment.7, 8, 9, 38
The chronicle · every date from a public document
How two months became four.
December 2021 · DOCUMENT
A contract for thirty-two months.
The Ministry of Infrastructure and Transport signs with the contractor Themeli: extend the runway 288 m northwards to 1,799 m, strengthen the existing 1,511 m, build safety areas at both ends. Thirty-two months. Funded by the Public Investment Programme and ESPA. A separate 6.7 million euro contract for the new terminal follows in August 2022; that building was delivered in 2025.2, 3
A single decision moves the deadline to the last days of 2026. By then the contract is five years old. No penalty clause is reported as activated.2, 59
Contractor: ΘΕΜΕΛΗ Α.Ε. · discount 24.79%
Duration: 32 months
Runway: 1,511 m → 1,799 m
20 January 2026 · QUOTE · Notis Mitarakis, MP for Chios
“FORABOUTTWOMONTHS”
Completion slips to 2027. The airport, he says, will close completely for about two months.5
420 M CLOSED (NORTH END)
TORA 1030 M
PROPELLER ACFT ONLY · LIMITED SEATS
13 March 2026 · ON THE RECORD
The runway shrinks. The island keeps flying.
Phase one begins. The same ATR 72s keep flying, but with fewer passengers on board: the airlines limit the load to what the shorter runway allows. Fares rise "from the day the NOTAM was issued", the Chamber of Commerce tells the Prime Minister a week later. But the planes keep coming, for six months.1, 36, 11
27 March 2026 · DOCUMENT
From now on, helicopters.
The C-130 can no longer land. ΕΚΑΒ writes to the Medical Association: every case will be covered by helicopter, newborns included. The nearest ΕΚΑΒ helicopter base is Syros, at least forty minutes away, or Elefsina. The Air Force Super Puma detachment at Chios airport stays, for now.52, 53, 54
June to August 2026 · ON THE RECORD
The summer falls away.
With fewer seats and higher fares, June departures fall 21 percent, July 21, August 31 against the year before. Hoteliers warn that tour operators "will not sign for 27 or 28". The year before, the airport had carried 321,269 passengers, for an island of 50,361 residents.13, 57, 22, 12, 35
6 October 2026 · SCENARIO · Politis Chios, unnamed sources
CLOSEDFROM15 NOVTO SPRING
"No NOTAM has been issued; it is a scenario under examination, not an officially announced decision." Airlines object. The ferry operator may cut Piraeus sailings from six to four a week.7
October 2026 · WHERE THINGS STAND
THE DECISIONHAS NOTBEEN TAKENYET.
A decision is expected within days. Before it is taken, this is the moment for residents, the authorities and the contractor to look at the same facts together.9, 38
Scenario · a Tuesday in December 2026, airport closed
Nothing dramatic happens. That is the problem.
The damage from a closure is not one event. It is a thousand ordinary days made longer, costlier and riskier. The people below are composites, but every situation is drawn from the public record.
Skylitseio runs a dialysis unit and a chemotherapy day unit, but complex oncology, specialist follow-up and surgery mean Athens. Islanders with chronic conditions "travelled regularly to the capital for treatment and tests", as an MP for the island put it in Parliament this week. With flights, a day trip. Without them, each appointment is an overnight ferry, a hotel, and a return boat that may not sail in a north wind.20
Skylitseio is the island's only public hospital, and it is short of staff. Serious cases are transferred to Athens. Until March the runway took fixed-wing air ambulances: a King Air in November 2025, a C-27J with six injured children in February 2026. Since the shortening, ΕΚΑΒ has told the Medical Association in writing that every case goes by helicopter, and the nearest ΕΚΑΒ helicopter base is Syros, at least 40 minutes away. Helicopters land at the airport; the hospital lists no helipad. A full closure removes the last fixed-wing option.21, 23, 24, 52, 53, 62
Spring bookings are made in winter. "None of the tour operators will sign," the manager of the Chandris Hotel told a public meeting in April, warning that the 2027 and 2028 seasons are at risk. Lost bookings do not come back when the runway reopens; they are already on Lesvos or Samos.22
"Our patience is running out." In January the Tourism Body asked for delivery by spring 2027. In October its president said he would accept any closure date on one condition: that the airport is ready for Easter. Kostas Moundros, president of the Chios Tourism Body, January and October 202633, 50
2 May 2027 · Orthodox Easter · the promise
"Clearly, at Easter and in summer the airport will be operating."
The MP's commitment on 7 October: a 1,500 m runway before Easter 2027, the full 1,800 m in summer 2027. The Tourism Body says it will accept any closure date on one condition: that the airport is ready for Easter. The island has heard dates before. This page exists so that the next one is written down.9, 50
Geography · where the island sits
Chios is 200 km from Athens and seven nautical miles from another country.
Athens is a 50-minute flight.
Or a night at sea. The only alternative is the overnight ferry from Piraeus: seven to nine hours, five to seven sailings a week, fewer in a hard winter. There has been no high-speed boat on the route for years.14, 15
The nearest airport is on another island.
Mytilene on Lesvos is two to three hours by ferry, almost daily. Samos is two to four hours but only two to five sailings a week. Neither link was designed to feed an airport, and neither airline schedule waits for a boat.16, 17
Izmir's airport is closer than any Greek one.
Çeşme is seven nautical miles across the strait, 30 to 45 minutes by ferry, and about 90 km from İzmir Adnan Menderes Airport. In winter the crossing runs about once a day. During a closure, the fastest route from Chios to a jet is through Turkey.18, 19
The alternative · Is another way possible?
The phased plan was the official plan. Whether it can still be followed is a question worth answering together.
Since 13 March 2026 the airport has run on a shortened runway: 420 m closed at the north end, 1,030 m of take-off run available, the usual ATR 72s flying with fewer passengers. That was ΥΠΑ's phase one. Phases two and three were to move the works south and keep a shortened runway open, around 880 m. The scenario now under discussion merges those phases into one long closure. Here is what the public record says about whether the phased route remains possible.1, 36, 9
What has been said so far about the need for a closure
A technical account of why a shortened runway cannot stay open has not yet been published. The reasons given so far are speed, and whether airlines would use a very short strip in winter.
"Technically impossible" not to close
Themeli's representative told the Municipal Council that independent authorities control the works and no other technical solution is permitted. No written breakdown followed. On 8 October the company was declining to comment.37, 38
Partly open means slower
ΥΠΑ warned that if the airport stays partly open "construction will fall very far behind". Its 9 March announcement promised separate NOTAMs for phases two and three with completion in the first quarter of 2027.39, 1
An 880 m strip "has no practical benefit"
Notis Mitarakis said the original plan was to shift and shrink the runway to about 880 m in late October; the alternative is to run two phases in parallel. Keeping the airport nominally open on a very short runway is pointless, he said, if airlines will not fly it in winter.9
So the open question is about 880 m, not about phasing. A 1,030 m configuration worked for six months. What has not yet been explained is why it cannot be held while the south section is built, and how many weeks the tie-in itself requires. That explanation would let everyone discuss the same facts.
What the rules and other airports show
Rebuilding a runway in phases while it stays open at reduced length is standard, documented practice. The regulators write guidance for it and Greek airports did it last winter.
Phased, reduced-length operation is the textbook method
The guidance describes works "divided up into phases where different parts of the runway remain operational with a reduced length available", temporary thresholds and lighting, night working, and asphalt ramps across the join so the runway reopens each morning. EASA's aerodrome rules cover partial closures and temporary displaced thresholds.41, 42
Full rebuild, 120 m extension, open throughout
A 1,463 m runway was completely reconstructed, a 1.5 m dip filled with 45,000 tonnes of asphalt and a new 120 m section added, "while maintaining full airfield operations throughout". Work ran at night with temporary ramps and the airport reopened at 06:30. Four short closures of about two and a half days each.43
Reduced length, not closure
Mykonos operated at 1,400 m of 1,902 m. Rhodes at 1,900 m of 3,300 m. Chania at 1,900 m with a displaced threshold. Where Fraport closed fully, it was for 14 days at Kefalonia, Corfu and Zakynthos and 7 at Santorini. Mytilene will close one day a week from 17 November 2026 to 23 March 2027, not for months.31, 45, 46
What the aircraft can do
ATR's figures for the ATR 72-600, the aircraft that serves Chios, are a take-off field length of 1,315 m at maximum weight and a landing field length of 915 m. Take-off is what limits it, and the way round that is weight: fly with fewer passengers. That is what the airlines did on 1,030 m for six months. The smaller ATR 42-600 needs 1,107 m at maximum weight and 966 m to land, so swapping types buys little. On 880 m the margin shrinks for both, and winter wind and a wet runway eat into it. That is a genuine argument against an 880 m strip. It is an argument for keeping 1,030 m, not for closing.30, 29, 36, 11
What will not replace the airport
Several substitutes have been floated. The record on each is short.
Greek runway works, winter 2025–26, as published by Fraport Greece and OPSGROUP.31, 45
What we are asking for
Five things we would like to see before any NOTAM is issued.
Publish the engineering case
Before any NOTAM, ΥΠΑ explains why the 1,030 m set-up that worked for six months cannot be kept, and how many weeks the tie-in needs.
Make the closure short and bounded
If a closure is unavoidable, it lasts weeks in deep winter, with a published end date and clear commitments if the dates move.
A substitute that actually sails
One extra Piraeus sailing a day, agreed in writing with the ferry operator before the closure, subsidised if needed.
Patients first
A written ΕΚΑΒ airlift plan, the Super Puma kept on Chios, and the airport open to helicopters throughout the works.
Pay for the delay
Transport Equivalent on Chios air fares for the duration of the works, and support for the 2027 season agreed now.
Act · decision expected mid-October 2026
Let’s talk before the decision.
This page was made by a resident of Chios, with no party or company behind it. It gathers the public record so that residents, the Ministry, ΥΠΑ, the contractor and the island’s MPs can discuss the same facts. A short, courteous message from a resident, a doctor, a hotelier or a student helps open that conversation. Copy the message below and send it, or share this page.
As a resident of Chios, I would like to ask that, before any NOTAM is issued, the reasons be published why the 1,030 m configuration that has worked since March cannot be kept while the south section is built, and how many weeks the tie-in needs. If a full closure is unavoidable, I ask that it be measured in weeks, in deep winter, with a published end date, as at Kefalonia, Corfu and Zakynthos; that one extra daily Piraeus sailing be agreed with the ferry operator in advance; that ΕΚΑΒ’s helicopter plan be published and the airport stay open to helicopters; and that the Transport Equivalent ceiling on air fares be raised for the duration. Thank you for considering this. — a resident of Chios